Solution: Laos Five Star Hotel Swimming Pool Project
The hotel was built by Laos Jadapeng Group Co., Ltd. and will be one of the reception hotels of the 9th Asia-Europe Summit held in Vientiane, Laos in early November 2012. It is of great political significance.
The swimming pool project started in July this year. The swimming pool specifications are: length 50m* width 15m, water depth: 0.9m-1.5m, cycle: T=6 hours, irregular swimming pool, and a diameter 2m, a circular massage pool with a water depth of 1m.
The swimming pool project's circulating filtration system uses three high-speed filter sand cylinders with a diameter of 1.4m and a height of 1.58m, and four 3.4kw circulating water pumps. The swimming pool disinfection system uses automatic and manual dosing.